FPSO Baobab Ivoirien MV10 Deck Reinstatement

 

Project Type

Deck Reinstatement

Location

Offshore, 25km from the Ivory Coast

Date

2017-2018

Team

Modec

©If required

In 2017, Modec faced a major maintenance challenge: its ABS-classed FPSO Baobab Ivoirien MV10 needed significant deck reinstatement to maintain structural integrity and keep operating safely. The complication? The vessel sat 25 km off the coast of Côte d’Ivoire, so every part of the repair had to happen offshore.

Modec ultimately chose SPS for the project because its COLD WORK repairs can be carried out while a vessel stays offshore, so production and operating schedules continue without disruption.

Using this method, SPS permanently reinstated several deck areas on the vessel, concentrating on the B, C and D decks, the wheelhouse and the upper deck. Because the repairs do not require heat input — unlike conventional welding — the team minimised downtime while keeping personnel on board safe.

”The SPS low heat input solution was selected for the upgrade of the accommodation and upper deck reinstatement on FPSO Baobab Ivoirien MV10. SPS caused minimal disruption to onboard operations.

Saw Kean HuahProject Manager (MMS), Modec

The SPS Deck Reinstatement Process

The team used SPS COLD WORK repairs to reinstate the steel deck plates, which ranged from 6 to 8 mm thick, restoring structural integrity without introducing unnecessary thermal stress.

First, they bonded perimeter bars to the existing deck with specialised structural adhesives, forming airtight cavities. The team then filled these cavities with a 25 mm elastomer core, giving the new deck plates additional stiffness and stability.

Throughout the deck reinstatement project, SPS Technology network partner ASOM supervised. Their team of experts ensuried the project was successfully completed over a three-month period. All the while, the vessel remained in operation with no interruptions to onboard systems.

”The selection of SPS means minimal heat input into the existing deck. The associated risks were accessed and the use of SPS eliminated below deck work. This significantly reduced downtime and costs.

Mohammad FarihimSPS Operations Manager
  • Previous ProjectPetrojarl Foinaven Hull Repair

  • Next ProjectDropped Object Protection